Hosting capacity is the amount of new generation or load that one specific part of the distribution system can accept under the utility’s stated criteria before a constraint is violated. The result belongs to a feeder, a line section, or another studied component, and to the scenario the utility modeled. It is not a universal kilowatt threshold. A public map shows a screen of that result. The interconnection study, not the map, is what approves a project.
Read the color as one utility’s screen for a feeder or studied component, ask whether the case is generation or load and which constraint is tighter, and leave approval to the interconnection study rather than a closed or restricted label.
The bars repeat the illustrative thermal case and voltage case already compared on this page and are not a utility measurement.
One result, several official meanings
The National Laboratory of the Rockies hosting-capacity page, last updated May 20, 2026, defines hosting capacity as the distributed photovoltaic generation that can be added before control changes or upgrades are required. The page says this is not a hard limit: upgrades increase what the system can accept. The result depends on system size and location, advanced inverter settings, other resources on the circuit, the equipment then in place, and the utility’s rule for when a mitigation is required.
EPRI’s April 2015 white paper defines it as the photovoltaics that can be accommodated without affecting power quality or reliability under existing controls and infrastructure. EPRI’s method produces a range, not a single feeder value. The low end is the amount that stays inside the studied limits no matter where the generation is placed. The high end is reachable only at favorable locations. A map that prints one figure has already chosen an end of that range, or a scenario. The legend has to say which.
The Department of Energy’s atlas of hosting-capacity maps extends the idea to generation or load at specific locations, and it says the maps do not answer site-specific interconnection questions. The Department states that it does not maintain the maps. Its table is dated May 2024 and is not a live inventory.
Maryland law uses a generation definition. COMAR 20.50.09.02, as reprinted by the Legal Information Institute with an amendment effective December 12, 2024, defines hosting capacity as the aggregate generation that can be accommodated on a distribution system, area, or system component without infrastructure upgrades. The same chapter treats parallel storage equipment as part of a small generator facility. A charging-only load is not that case. Virginia and the District are outside this Maryland chapter. Confirm the official regulation text before a filing; this reading is the Institute’s reprint, checked November 22, 2026.
What the analysis actually tests
The calculation compares power-flow cases with limits the utility chooses. EPRI’s 2015 method centered on voltage, including regulator and capacitor operations, and on protection, including relay desensitization, sympathetic tripping, and fault duty. Thermal overload mattered when reverse flow stressed a line or transformer. A share-of-peak-load shortcut could overstate or understate the result.
The laboratory page separates snapshot analysis from dynamic analysis. A snapshot uses a few static moments, often maximum photovoltaic output at the same time as minimum load, which the page describes as unlikely in ordinary operation and typical of public maps. Dynamic analysis uses time series and can allow brief overvoltage or thermal overload. As of the May 20, 2026 update, the laboratory still described dynamic hosting capacity as under development. Do not assume a utility map used it. If the legend is silent, read the color as a conservative snapshot.
As of November 2026, Dominion Energy’s hosting-capacity tool says its analysis considers thermal limits, reverse-power-flow specifications, and voltage effects, segment by segment. The same page says the map does not consider how distributed resources affect voltage-regulating devices, including substation and line regulators and transformer load-tap changers. Dominion states that an interconnection study is required to confirm the map. The omitted criterion is the point: a screen can be internally consistent and still leave out a check the study will run.
COMAR 20.50.09.06, in the same Institute reprint and effective amendment, requires a calculation procedure that accounts for either gross peak loading or gross minimum loading, using good engineering practice. It also requires a sample of validation checks at least annually, and more often where growth or distributed-energy penetration is significant. A new color is not evidence that every span was field-checked that week.
Why two neighboring feeders disagree
EPRI’s April 2015 paper compared two feeders that looked similar at a high level: one could accept any studied photovoltaic deployment up to 2.2 MW, about 30% of that feeder’s peak load, while the other was limited to 0.5 MW, about 16% of its peak load, unless location was favorable. Those are the paper’s research feeders, not Pepco, BGE, or Dominion circuits, and they are not a planning limit for a 2026 project. The lesson is that peak load and a shared label did not predict the result.
EPRI traced the difference to resource size and location, feeder characteristics, and technology. A single plant is not the same stress as the same megawatts spread along the feeder. Voltage class, load placement, conductor, voltage control, and protection all matter, and inverter-based generation does not feed faults the way a rotating machine does. A network that trips on reverse flow can reject export while a nearby radial feeder still shows room.
The inputs also age. Feeders are reconfigured, generation is added, and conductor or regulation changes. As of November 2026, Dominion says its current analysis excludes projects that are not yet connected and excludes planned infrastructure. A line can look open while applications already in process will use the margin. Record the legend date with the screenshot.
How to use a map in this region
Use the utility that serves the meter. County lines do not follow Pepco, BGE, Dominion, Potomac Edison, SMECO, or NOVEC. The Department of Energy atlas, in its May 2024 table, listed map entries for BGE, Pepco, Potomac Edison, SMECO, and Delmarva in Maryland; Pepco generation and electric-vehicle entries for the District; and Dominion generation and electric-vehicle entries for Virginia. NOVEC was not on that Virginia list. Do not read a Dominion layer for a meter Dominion does not serve, and do not treat the atlas link as the utility’s current instructions. This research did not open the Potomac Edison or SMECO map applications, so their criteria are not described here.
As of November 2026, Pepco’s hosting-capacity page says the map indicates how much generation, in kilowatts, can be added to a feeder before capacity or other limits reduce reliability on that feeder. Pepco states that the values are a general indication, that space is not assured and may change at any time, that every application still needs a full review, and that the results may understate hosting capacity. On radial feeders, Pepco treats a system as large above 250 kW on 4 kV and 12/13 kV systems, above 500 kW on the 25 kV system, and above 1,000 kW on the 34 kV system. After the aggregate large limit, smaller systems may continue until another substation violation. In some Pepco Holdings jurisdictions, a circuit-specific reserve for small resources is removed before the clicked value is shown. Network feeders are a separate map. The page warns that New Jersey rules and levels may differ, so do not copy a network size limit from that page into a Maryland or District project.
As of November 2026, BGE’s PV hosting-capacity page indicates how much generation, in kilowatts, can be added in an area before the supplying feeders hit capacity or other reliability limits. BGE states that values are a general indication, may change, still require a full review, and may understate capacity. Any system over 250 kW is large. That aggregate large limit is circuit-specific. After it is reached, systems of 250 kW or smaller may continue until another circuit or substation violation. An area marked for contact with BGE is a pre-application, with address or coordinates and system size, not a number to interpret. Network generation goes to BGE’s interconnection team. BGE’s single 250 kW cutoff is not Pepco’s voltage-class cutoff.
Dominion’s tool, as of November 2026, covers its Virginia and North Carolina distribution system and is aimed at limiting voltage and thermal issues. The utility-scale map uses distribution lines and other distribution facilities, not distribution transformers, colors each section by that section and everything upline, and displays megawatts. The residential map uses the lower of that limit and the transformer size, and it does not include secondary conductor. A line or transformer with no remaining solar hosting capacity is omitted. That is a display rule, not an order from the Virginia State Corporation Commission. Dominion plans to refresh at least quarterly; the legend date is the update. The analysis excludes industrial and network feeders. The utility-scale map also excludes single- and two-phase lines, sections below 11 kV, and conductor near critical assets or customers. Dominion says the figure is a general siting assessment and that every project still goes through the application.
Match the layer to the project. A generation map does not size a new load, and a load map does not size export. The atlas lists those as separate Pepco and Dominion products. Record whether the symbol is a primary-line result or a transformer result, and whether a small-resource reserve was already removed.
Closed and restricted are not an approval
Under the COMAR section cited above, a Maryland utility designates a circuit closed when no hosting capacity remains, and restricted when only reserve hosting capacity remains. Reserve is set from a circuit-specific forecast or other factors, including customer density, area type, and customer demographics. Those designations belong in the utility’s reporting system. Closed means the current calculation shows nothing left. It does not, by itself, mean an upgrade is impossible. The regulation allows a utility to propose a hosting-capacity upgrade plan when forecast growth would congest an area. Who pays, and whether a plan exists, is a tariff and Commission question.
A high value is not permission to build or to operate. The binding limit may be a shared substation transformer, a transmission constraint, a protection change, or a secondary cable the hosting model did not include. The laboratory statement that upgrades can raise hosting capacity is not a commitment that a particular upgrade will be offered.
PJM Manual 14H, Revision 07, effective August 19, 2026, is the cycle process for new service requests to interconnect generation or transmission on the PJM system, through the request for facility construction. It does not calculate distribution-feeder hosting capacity. Dominion’s page describes distribution as the system that delivers energy from substations to customers, and says very large solar plants typically connect to transmission instead. The point of interconnection and the tariff decide the path. A favorable feeder color does not create a PJM request. A PJM request does not establish the hosting capacity of a feeder the plant will not use.
Soleil’s commercial solar interconnection guide explains commercial utility-approval steps. It is not the PJM manual, and neither a guide nor a map is permission to operate.
An illustrative pair of limits
This example is illustrative arithmetic. It is not a measurement, not a Soleil Energy project, and not a Pepco, BGE, or Dominion result.
Assume a screen prints the minimum of the criteria it tests. Thermal loading would allow 4 MW of additional export on a section, and the voltage case would allow 1.5 MW. The map shows 1.5 MW. Thermal room the screen does not award is:
4 MW − 1.5 MW = 2.5 MW.
In this illustration, moving the plant toward the substation could make thermal the binding limit. A second plant is not entitled to the leftover 2.5 MW, because location changes the power flow. A published zero can mean the voltage case failed first, so a different location, a smaller size, or a non-export design might study differently. It can also mean every practical case fails. A qualified engineer has to test the proposed point against the utility’s model.
Before the color becomes a site decision
| Question | What it changes |
|---|---|
| Which utility serves the meter? | Another utility’s layer is a different model and tariff. |
| Export or new load? | The published screen is not interchangeable. |
| Primary line or behind a transformer? | Dominion’s two solar maps answer different questions. |
| Large or small on that utility’s cutoff? | Pepco’s cutoff follows voltage class. BGE uses 250 kW. |
| Legend date, and are unbuilt applications in the model? | Dominion excludes generation not yet in service. |
| Closed, restricted, or only a low color? | Maryland defines closed and restricted as reporting categories. |
Collect the address, the proposed point of interconnection, and the capacity basis before treating a screenshot as a development choice. Soleil’s commercial solar site checklist is a way to assemble that record.
Soleil Energy’s utility-scale solar work includes the plant, the substation, and utility coordination for the interconnection. A scope discussion can use the utility name, the map and legend date, the proposed point of interconnection, the capacity basis, and whether the project is distribution-connected or transmission-connected. That discussion does not approve the project or replace the utility or PJM study. A qualified professional has to assess the site.
Questions that change the next step
What does a missing line mean on Dominion’s solar map?
As of November 2026, Dominion omits a line or transformer with no remaining solar hosting capacity. Absence is that display rule, not a Commission denial. Ask which criterion bound, and whether the feeder is in a class the tool excludes, such as network, industrial, or below 11 kV on the utility-scale map.
Why is BGE’s “large” cutoff not Pepco’s?
As of November 2026, BGE calls any system over 250 kW large, from a circuit-specific aggregate analysis. Pepco’s radial page uses 250 kW, 500 kW, or 1,000 kW depending on voltage class, and in some of its jurisdictions it withholds a small-resource reserve before displaying the remainder. Transferring one cutoff to the other utility’s feeder misstates both screens.
Does a Maryland closed circuit end the project?
It means the current calculation shows nothing left, and the circuit is supposed to be reported that way. A different point of interconnection, a smaller or non-export project, or an upgrade plan can still be studied, and the study can also find the facilities impractical. Check the reporting system and the application, not a saved color.
When is the PJM manual the wrong document?
Use Manual 14H for a PJM new service request on the PJM transmission system. Use the distribution utility’s path when the plant connects to a feeder. Some projects need both. The hosting-capacity map files neither request.
What should the screenshot file contain?
The serving utility, the map name, the legend date, and the date viewed. The feeder or line identifier, the voltage if shown, and whether the symbol is a primary result or a transformer result. Export versus load. For Maryland, whether the circuit is closed or restricted. Without those notes, a later refresh cannot be compared with the picture used to choose the site.
Project requirements depend on the site, equipment and applicable rules. Confirm design and installation decisions with the appropriate qualified professional.