P50 vs P90 solar yield compares two probability-of-exceedance estimates of the electricity a photovoltaic project is modeled to produce. P50 is the energy the stated distribution expects to exceed in half of the modeled outcomes. P90 is the lower energy the same distribution expects to exceed in nine out of ten modeled outcomes. Each figure applies only to its stated period and uncertainty stack. Neither is a production promise or the worst year on record.
Match the quoted figure to its period and uncertainty stack, treat P50 as the middle and P90 as a lower energy expected most of the time, and do not read either as the worst year or a production promise.
Choose the figure that matches the decision
A sponsor and a lender can quote different numbers from one study because they are answering different questions. The central case is the middle of the modeled distribution. A higher exceedance case is a lower energy the model still expects to beat most of the time. Financing institutions use both the P50 and the P90 when they judge repayment risk, according to the National Renewable Energy Laboratory report revised in March 2024 (Prilliman and coauthors, NREL/TP-7A40-84993).
That report does not assign one statistic to every US loan. The International Finance Corporation’s 2015 guide for utility-scale photovoltaic developers, prepared for IFC under contract, says investors most often ask for a P90 and that an independent specialist should prepare or check it. The guide’s one-year P90 is meant to express year-on-year resource swings when debt is serviced during the year. Its ten-year P90 is resource uncertainty over a ten-year period. The guide then says the choice depends on the financial structure and the financing institution (IFC project developer’s guide).
As of November 2026, that guide is not a US term sheet and not a federal rule. Read the credit papers for the quantity, the period, and the exceedance level the test uses. Dropping the central case leaves no reference for expected energy. Funding only on the central case accepts the half of the modeled distribution that falls short.
An exceedance value is a point on a distribution
In the March 2024 NREL revision, a probability of exceedance is the chance that annual energy in a future year exceeds a stated value. The P90 is the annual energy expected to be exceeded with 90% probability, and the P50 is the value at 50% (same NREL report). The IEA PVPS Task 13 report of April 2018 states the general form: Pxx is the value exceeded with probability xx percent (Reise and coauthors, IEA-PVPS T13-12:2018).
Sandia’s May 9, 2024 slides state the percentile form: P90 is the 10th percentile of the distribution of future annual energy (Hansen, SAND2024-06106 C). PVsyst’s documentation, read on November 22, 2026, says that inside its normal-distribution tool P90 is the 10th percentile and P50 is the median, equal to the mean (PVsyst P50 to P90 help). The definitions agree. The recipes that build the distribution do not.
The NREL report names P99 as the yield expected to be exceeded with 99% probability (Prilliman and coauthors). Summarizing external reports from 2020 through 2022, it says about one in seven evaluated systems fell short of their P99. NREL presents that pattern as a reason to improve uncertainty modeling. It is not a 2026 census.
It is not the worst year and not a production promise
If the model is right, about one future year in ten still lands below the P90. The lowest year in a sample can be lower than the P90 taken from that sample. In the 2012 System Advisor Model paper, hypothetical Phoenix plants had a minimum year below the empirical P90. That comparison of methods is not an operating record (Dobos, Gilman, and Kasberg, NREL/CP-6A20-54488).
An acceptance test has its own period, meter, exclusions, and remedies. An exceedance table does not write them. The December 2018 NREL and Sandia operations report includes a sample monitoring schedule that compares actual irradiance, production, and revenue with expected P50, P75, and P90. The same report describes a weather-risk contract that may follow irradiance rather than equipment (NREL/TP-7A40-73822).
The time period changes the number
Task 13 separates a single future year, the mean over the prediction period, and cumulative yield. An initial yield, its P90, a lifetime average, and the P90 of that average can be inadequate once degradation, an irradiance trend, and the time for high and low years to offset are in the model. In the report’s Monte Carlo example, interannual weather widened single years, while cumulative yield tightened within a few years because high and low years offset. Uncertainty in a long-term change rate does the opposite: small at first, larger later. Those paths use the authors’ assumptions over a 20-year life. They are not a gap to copy.
A one-year coverage test is not answered by a ten-year exceedance, and the average does not describe next year. NREL treats each historical weather year supplied to the model as equally likely to stand in for a future year, while allowing a long-term weather prediction in place of that assumption. PVsyst’s help page adds that the resource is not stationary and that its tool ignores dimming and brightening unless the user applies a shift.
How the distribution is built
The 2012 SAM paper starts from many simulated years. Under a normal fit, P50 is the mean and P90 is the mean minus 1.282 standard deviations. Sorting the years is preferred when volcanic aerosols or multi-year cycles skew the record, and the paper discusses that read once more than ten values are available. Hypothetical Phoenix plants in SAM version 2011.12.2, on 30 weather years after bad years were dropped, held the performance model fixed, so the spread is weather only. For those PV cases the normal P90 was a few percent more optimistic than the empirical P90, and the TMY2 annual total sat slightly above the P50 (Dobos, Gilman, and Kasberg preprint). The paper’s record at OSTI states the purpose as quantifying financing risk from interannual variability (OSTI 1044455). A TMY file, the paper explains, stitches typical months and drops outlier months. Those dropped periods can be what a downside case needs. A TMY total can sit near a P50 and still not be one, and it is not a P90.
The March 2024 errata separates weather, which more data will not remove, from models and measurements, which better information might shrink. Annual factors may follow any distribution. A base energy, possibly a TMY run, is scaled by independent factors, each historical year is run at the nominal model, and the pooled sample is sorted. The report’s sample-size rule requires more than 100 draws for a 10th-percentile P90.
Sandia’s 2024 slides call the older habit an all-in approach: one P90 that does not separate irreducible weather from uncertainty better measurements could shrink. The split can leave the overall P90 unchanged while showing which part is which, and the slides treat modeler skill as a contributor.
PVsyst’s help page is one product’s method, not a consensus standard. It centers a normal curve on the simulation, adds uncertainties in quadrature, and places P90 at 1.28 standard deviations below the mean. Those extra terms are year-to-year randomness, not doubt in the long-term average, and the page calls long-term degradation incompatible with that P90 concept. Sensor and satellite bias sit outside the variability term, so the suggested check is a second weather provider. A specific year is not a P50 unless the user shifts it. The page also rejects scaling every hour by the annual P90-to-P50 ratio: a lower year is a different pattern of poor weather, not a uniform shrink of clear hours.
What belongs in the stack
NREL’s first-order factors are transposition to the module plane, horizon and row shading, module power at standard test conditions, and inverter availability. Second-order factors are spectrum, cell temperature, mismatch, and electrical loss. The narrative leaves soiling, snow, and transformer performance without distributions, while the default table includes soiling and transformer values from Task 13 and still omits snow. Use the factor list the run actually used.
Task 13’s example adds reflection, cabling, power limitation, long-term behavior, an irradiance trend, and annual variation. Several distributions are one-sided so soiling or shading cannot appear as a gain. Independence is called a simplification. With asymmetric terms, the P50 can move away from the single deterministic run, and that gap can grow over the prediction period.
Grid export limits are absent from the NREL list and from that example. The IFC loss table uses “curtailment” for tracker stow in high wind, not for an interconnection cap. Ask whether an export limit is inside the nominal case, inside the uncertainty, or in neither. Do not enter availability or soiling twice: the nominal loss is the central assumption, and the uncertainty term is only the remaining doubt. The IFC guide ties soiling or snow to the operations contract. Degradation is a path through time. A later year that only applies a fixed schedule to the year-1 P50 is deterministic unless uncertainty in the rate was propagated. Name the meter boundary as well. Wiring and transformer losses are in the chain, so inverter energy and revenue-meter energy differ.
Why one expected total misleads
One annual total does not say whether it is a P50, a mean, a TMY run, one historical year, or a lifetime average. The September 4, 2014 PVWatts Version 5 manual says to read the result as a representative estimate for a similar grid-connected system in typical weather. It states that errors may be as high as 10% for annual totals and 30% for monthly totals under long-term typical weather, and that a specific year may depart from that average by as much as 20% annually and 40% monthly (PVWatts Version 5 manual). Those are the manual’s stated possible errors for that model. They are not a P90, not a measured error for a named plant, and not an exceedance distribution.
An illustrative normal-distribution calculation
The following arithmetic is illustrative. It is not a site, not a Soleil Energy project, and not a typical gap between P50 and P90.
Use only the 2012 normal shortcut. Suppose the modeled annual energies have a mean of 100,000 MWh and a standard deviation of 4,000 MWh, and P50 is that mean.
1.282 × 4,000 = 5,128
100,000 − 5,128 = 94,872
The illustrative P90 is 94,872 MWh. The spread was assumed, and the subtraction omits transposition error, soiling, availability, curtailment, resource bias, and degradation. Drop the normal assumption, as the Phoenix cases did, and the result moves. There is no universal distance between the labels.
Compare the basis before comparing the gap
A narrower gap is not a safer plant. It shrinks for a multi-year total, a quiet weather sample, or a short factor list, and it widens when skewed losses, a change-rate uncertainty, or a second weather provider moves the result.
| Question | What a different answer changes |
|---|---|
| One year, a ten-year resource case, a lifetime mean, or a cumulative total? | Weather dominates one year. Offsetting years narrow a cumulative total. A rate error grows later. |
| Which files, and is the past standing in for the future? | A TMY stitch is not a P90 sample. Long-term bias can shift every year together. |
| Normal shortcut, empirical years, or pooled factors? | The 2012 Phoenix cases split the first two. The 2024 revision adds the third. |
| Nominal losses versus uncertainty around them? | Entering soiling or downtime twice moves the center and the width. |
| Export limits, snow, availability, degradation? | Missing from a default list is not a studied zero. |
| Electrical boundary? | Inverter energy and revenue-meter energy are not interchangeable. |
| Does P50 equal the unmarked simulation? | Asymmetric terms can pull them apart over time. |
NREL’s executive summary says inconsistent proprietary methods reduce investor confidence and raise perceived project risk. The sample, the factors, and the period show whether two numbers are the same object.
Shading, spacing, and soiling are site facts. Soleil Energy’s commercial solar site checklist covers sun exposure and rooftop obstructions for a commercial building. A utility-scale layout needs that class of record for its own terrain; the checklist itself is written for buildings. Export caps are separate. The commercial solar interconnection guide explains that utility review and wholesale-market participation are separate decisions, and it focuses on Maryland. It is not a project-specific study. A cap can remove energy the yield file never treated as uncertain.
Frequently asked questions
Is a P90 the worst year the plant will see?
No. If the model is calibrated, about one year in ten still falls short, and the worst file year can be lower. Snow, an export cap, or a climate shift that was never coded is outside the percentile.
Does a small P50-to-P90 gap mean lower risk?
Not by itself. Task 13’s cumulative example tightened over a few years while single years stayed wide. A short factor list also looks tight. A small gap that omits resource bias or availability is a narrower story, not a safer plant.
Can a typical-year calculator replace a P90?
No. The 2014 PVWatts manual gives a representative total and states possible errors. It does not report an exceedance. A TMY file can exclude the outlier months a downside case is for. Use it to screen. Do not relabel it.
Which P90 should a financing case use?
Match the test. The 2015 guide links a one-year P90 to debt service during the year and a ten-year P90 to a longer resource view, then leaves the choice to the institution. As of November 2026, read the draft credit documents rather than importing that wording unchanged.
Why do two studies of one plant disagree?
They may not estimate the same object. Providers can disagree on the long-term average, a normal shortcut can sit above an empirical P90, and one figure may be year one while the other is a lifetime mean. Sandia’s 2024 slides treat the modeler’s parameter choices as part of the uncertainty. Compare period, weather years, factors, and meter boundary before calling the difference a site fact.
Does a strong first year confirm the P50?
No. One year is one draw. A high year does not prove the downside tail, and one low year does not prove bias. NREL’s note on systems that missed a stated P99 shows how omitted losses can land outside a published tail. Match the meter and the exclusions, and use enough years to see weather rather than one season.
Bring the yield basis into the plant scope
Layout, inverter loading, row shading, soiling access, and the delivery point all change the nominal run before a probability is calculated.
Soleil Energy’s utility-scale solar practice covers engineering, procurement, construction, interconnection, commissioning, and operations in that scope, as principal or specialist depending on the project. A useful next step is a project-scope review using the site, the capacity basis, the interconnection position, and the yield report’s cases, period, boundaries, and exclusions. The review does not replace an independent energy assessment, and it does not set a production commitment. It asks the plant being designed and the energy figure being financed to describe the same project.